top of page

Oakland Business Park

Industrial

Market

$32.7M

Value

Orion, MI

Location

2020-2022

Year Completed

Interior Renovation

Type

283,500 sq ft.

Size

Architect:

OBP A - Shremshock Architects Inc. Timothy Shremshock
OBP B - Auger Klein Aller, Architects Inc. Brad Klein
OBP C - Shremshock Architects Inc. Timothy Shremshock

Henry Yandt Construction successfully built out 250,000 square feet of industrial manufacturing space in three existing shell structures at Oakland Business Park.

Henry Yandt Construction proudly delivered a large-scale, multi-phase industrial development at Oakland Business Park, transforming over 250,000 square feet of existing shell structures into advanced manufacturing facilities. Spanning three distinct single-story buildings—OBP A, B, and C—this ambitious $32.7 million project required expert coordination, precision, and innovation to meet the specialized demands of industrial users while optimizing infrastructure and utility systems across the entire site.

Working within the constraints of existing shells, our team executed an intricate build-out that integrated heavy mechanical, electrical, and plumbing systems tailored for complex manufacturing operations. We combined structural enhancements with comprehensive site improvements to create a cohesive, high-performance industrial environment. Each phase of this project reflected our dedication to functional excellence, from foundational utility work to interior steel platforms designed to support HVAC equipment and process piping.

Construction Highlights:

  • Complete sitework including new watermain, sanitary sewer, storm water management, hardscape, and landscaping.

  • Steel-framed buildings with metal panel veneer and standing seam metal roofing.

  • Interior construction featured underslab utilities with 6” slab-on-grade concrete for durability and load-bearing capacity.

  • Full interior build-outs of offices, labs, bathrooms, break rooms, and industrial storage spaces.

  • All three buildings were fully equipped with wet fire suppression systems for safety compliance.

  • Interior steel platforms for mechanical systems and HVAC integration, enabling seamless operations.

Project Details:

  • OBP A – 87,786 SF | Completed: 06/30/2022 | Budget: $5.2M

  • OBP B – 72,616 SF | Completed: 12/17/2020 | Budget: $22M

  • OBP C – 123,167 SF | Completed: 12/30/2022 | Budget: $5.5M


The Oakland Business Park project exemplifies our ability to lead complex industrial developments with technical proficiency and strategic foresight. By delivering versatile, high-capacity facilities, we’ve empowered our client’s growth while contributing to the broader advancement of Oakland’s industrial infrastructure.

Progress Photos

CONTACT US

Reach out with any
questions or inquiries

Thanks for submitting!

ADDRESS

1615 S. Telegraph Rd.
Bloomfield Hills, MI 48302

PHONE

(248) 520-2229

EMAIL

  • LinkedIn

© 2025 by Henry Yandt Construction.

bottom of page